• Project: Sierra High School Renovation
    Projected Completion Date: Summer 2023
    Budget: $14,307,200

    Comments (-1)

Updates for August 1, 2019

    • Boiler Replacement project is complete and will be fully operational by start of school.
    • Additional project was added to accommodate blown electrical service into the High School
    • The school is currently on temporary power.
    • Parts are on order (secondary switchgear) and engineering team is determining when to make the switch back to building power.
    • Chiller Project will occur in late-October and end in December, bids are due August 9th.